Oct 6, 2026

Can ER70S-6 Be Used for P22 Steel?

Can ER70S-6 be used for P22 steel? Learn why ER70S-6 is not normally recommended and what to check before using it for P22 welding.

202609_WH_800x800px
Normally, no. ER70S-6 should not be used as a general-purpose welding wire for P22 steel.
ER70S-6 is a solid carbon-steel welding wire, while P22 is a Cr-Mo alloy steel used in elevated-temperature applications.
The important distinction is simple: ER70S-6 may be able to make a weld on P22, but that does not mean it is suitable for P22 service.

Why Is ER70S-6 Not Normally Used for P22?

P22 welding requires the deposited weld metal to meet the requirements of the joint and its service conditions.
ER70S-6 is primarily intended for carbon and mild steel welding. Its weld-metal system is therefore different from the filler metals normally selected for Cr-Mo steel applications.
Using ER70S-6 on P22 may affect:
  • Weld-metal chemistry
  • Mechanical properties
  • Elevated-temperature performance
  • PWHT response
  • WPS/PQR qualification
  • Code and project compliance
For more background on using carbon-steel wires with Cr-Mo steels, see our guide to carbon steel welding wire for Cr-Mo steel.
This is why visual weld quality alone is not enough to determine whether ER70S-6 is suitable for P22.

Can ER70S-6 Be Used on a P22 Joint?

It can only be considered when the specific application has been evaluated and qualified.
Not every P22 joint has the same requirements. A P22 component may be welded to P22, carbon steel, or another alloy steel. Filler-metal selection can therefore depend on:
  • Base-metal combination
  • Joint design
  • Service temperature
  • PWHT requirements
  • Required weld-metal properties
  • Applicable welding code
  • Qualified WPS/PQR
For example, a dissimilar-metal joint may require a different welding strategy from a P22-to-P22 joint.
Therefore, ER70S-6 should not be treated as a universal substitute for the filler metal specified by the welding procedure.
For normal P22 filler-metal selection, see our P22 welding consumables selection guide.

What If ER70S-6 Is the Only Wire Available?

Do not change to ER70S-6 simply because the specified P22 welding wire is unavailable.
Before making a substitution, verify:
  1. Base materials – What materials are being joined?
  1. Service conditions – What temperature and service environment will the weld see?
  1. Weld-metal requirements – Does the deposited metal meet the required properties?
  1. PWHT – Is post-weld heat treatment required?
  1. WPS/PQR – Is the proposed consumable covered by the qualified procedure?
  1. Code and specification – Does the applicable code or project specification permit the proposed filler metal?
If these requirements have not been evaluated, ER70S-6 should not be selected as a simple replacement.

ER70S-6 for P22: Quick Answer

Question
Answer
Can ER70S-6 physically weld P22?
Yes
Is it normally recommended for P22?
No
Is it a general substitute for P22 filler metal?
No
Can it be used in a qualified application?
Potentially
Can it be substituted without procedure review?
No
The key point is:
Weldability does not automatically mean service suitability.
For P22, the filler-metal decision must consider the weld metal, service conditions, heat treatment, applicable code, and qualified welding procedure.

FAQ

Can ER70S-6 be used for P22 steel?

Normally, no. ER70S-6 is primarily a carbon-steel welding wire and should not be considered a general-purpose filler metal for P22.

Can ER70S-6 physically weld P22?

Yes. However, the ability to deposit a sound weld does not prove that the weld metal meets the requirements of the P22 application.

Can I use ER70S-6 if the specified P22 wire is unavailable?

Not automatically. Review the applicable code, project specification, weld-metal requirements, and WPS/PQR before making a substitution.

What is the main concern with ER70S-6 on P22?

The main concern is whether the deposited weld metal provides the required properties and service performance for the P22 component, including after any required PWHT.

Conclusion

ER70S-6 is not normally recommended for P22 steel.
Although it can physically weld P22, its suitability must be established from the weld-metal requirements, service conditions, PWHT, applicable code, and qualified welding procedure.
If a suitable P22 welding wire is required, see our ER90S-B3 welding wire for P22/T22.
If ER70S-6 is being considered as an alternative, treat it as a welding procedure and qualification decision—not simply a wire-availability decision.

Read next

More from the journal

Keep readers moving through related announcements, stories, and field notes.